Getting a Finnish trial site ready after authorisation in CTIS

← All articles

When Finland’s decision comes through in CTIS, the next question is when the first participant can be seen. The decision has to be in place first, but on its own it does not make the site ready. The hospital may still need to issue its own research permit, the site agreement may not be signed yet, and staff, supplies and system access all need checking. The points below assume a medicinal product trial in Finland.

Start from Finland’s decision

Under the Clinical Trials Regulation (EU) No 536/2014 (CTR), the reporting Member State assesses Part I of the application and each Member State concerned assesses Part II for its own territory (Articles 6 and 7). In Finland, Fimea and Tukija take part in this work. Finland then sends the sponsor a single decision through CTIS: authorised, authorised subject to conditions, or refused (Article 8). A favourable Part I conclusion is not, on its own, Finland’s authorisation. See also clinical trial regulations in Finland.

Check that the Finnish decision covers the sites and investigators you plan to use, which protocol and participant document versions were authorised, and whether conditions are attached. Article 8(1) only allows conditions that by their nature cannot be met at the time of authorisation. Give each condition an owner and a due date, and decide where the evidence will be filed. Some will block a specific activity, such as enrolment; others have a later deadline.

Keep one controlled list of the document versions the site should use, and check training slides, pharmacy instructions and the investigator site file against it.

Keep the hospital permit and the agreement separate

Trial authorisation, the institution’s research permit and a signed site agreement are separate things, and each needs its own line in the tracker. Processes differ between institutions, so ask each one early which permits and contracts it requires, who applies, and what has to be done first.

Helsinki University Hospital (HUS) is one example. Clinical Research Institute HUCH, which signs research agreements with sponsors, states that the negotiated agreement “is also needed to apply for the final HUS research permit”. When a new study is planned, the researcher makes a preliminary check that HUS research nurse resources are available, along with special services such as pathology and imaging, and the principal investigator lists the HUS services needed in the permit application. That is the HUS sequence. It is not a rule or timeline for every Finnish site.

HUCH also notes that agreements and budgets often need lengthy negotiation. Check the budget against what the protocol actually asks of the site. Pharmacy, samples, imaging, participant travel and out-of-hours work can sit with different departments, so agree who provides and pays for each.

Check participant documents and languages

The CTR leaves the language of the application dossier to each Member State (Article 26). Information for participants must be understandable to a layperson and given in a prior interview with a qualified member of the investigating team, during which it is verified that the participant has understood it (Article 29). Check Tukija’s current instructions before finalising Finnish documents.

Compare the information sheet, consent form, recruitment material and visit instructions with the authorised set, and include the smaller items that are easy to miss: appointment letters, diaries and contact cards. Check which language versions you have (Finnish, Swedish or others your participants need) and how superseded versions are taken out of use. If an interpreter is needed, agree the arrangement before the first approach.

Walk through the first visit

Go through the first planned visit step by step with the investigator and site team: who checks eligibility, who holds the consent discussion, who processes samples and who enters the data.

ICH E6(R3), in effect in the EU since 23 July 2025, is the reference here. The investigator should have enough qualified staff and adequate facilities (section 2.2.2), make sure the people they delegate activities to are qualified (2.3.2), keep a record of those delegations (2.3.3) and maintain oversight (2.3.1).

Then check the room, equipment, investigational product, sampling kits and courier collections. For kits, check that they are the right ones, in date, and that the current lab manual goes with them.

Test that each user can do their own tasks in the eCRF, the randomisation system and other platforms, and agree how monitors will access source records under the institution’s rules. The investigator or institution should control the essential records it generates (ICH E6(R3) 2.12.11), so agree the site file arrangements at this stage as well.

Site readiness checklist

Record the owner, status, evidence location and next action for each item. This is a working aid to adapt to the trial. It is not a regulatory form.

  • Finnish decision: decision and conditions reviewed; authorised document versions listed.
  • Institutional permission: research permit or other local approval confirmed and on file.
  • Agreement and budget: signatures in place; services and payment responsibilities agreed.
  • Participant documents: current versions available in the languages needed.
  • People: investigator and staff available, trained and delegated to suitable tasks.
  • Product and equipment: supplies released, stored correctly and supported by working instructions.
  • Laboratory and samples: collection, processing, storage and transport tested.
  • Systems and records: access tested; source data locations and essential records agreed.
  • Safety communication: contacts, escalation routes and reporting instructions understood.
  • Activation: open items assessed and the sponsor’s release process completed.

Make the go-live decision explicit

The initiation visit is the place to settle questions and complete training, but holding the visit does not mean the site is ready. For anything still open, note its possible effect on participant safety, protocol compliance or data reliability, and whether it blocks the planned activity. An unmet authorisation condition still applies even when everything administrative is in place.

Agree who releases the site under the sponsor’s procedures and how the decision reaches the investigator and pharmacy. Keep the record of what was checked. It is the baseline for ongoing monitoring when amendments or staff changes come later.

Also decide who submits the CTIS notifications. Under Article 36, the sponsor notifies each Member State concerned, through the EU portal, of the start of the trial and of the first visit of the first subject in that Member State, each within 15 days. The start of a trial is the first act of recruitment of a potential subject unless the protocol defines it differently (Article 2(2)(25)), so it is not automatically the initiation visit date.

How RecQ can help at your Finnish site

RecQ’s own team prepares CTIS applications and ethics committee and Fimea submissions, and negotiates research permits and site agreements with hospitals in Finland and the other Nordic countries. Our CRAs carry out site initiation and monitoring, and we have more than 20 study nurses in different regions of Finland, including harder-to-reach locations. Finnish- and Swedish-speaking CRAs write and check participant documents, and we translate trial documents into every Nordic language. We also handle local logistics, such as transport of study materials and participants’ travel. See all our services.

Where a hospital charges for monitors’ read access to its patient record system, such as Apotti, RecQ pays the licences for its CRAs, who use that access on site at the hospital.

Tell us where the trial stands, which sites are planned, when you want the first visit and what is still open, and we will tell you which parts we can take on alongside your sponsor or CRO team.

Request a proposal